FY 26-27 (Year 9)

Sales Tax Revenue
JULY 2026 - JUNE 2027

Planned Projects

*Revenue estimates and projects are subject to modification as actual data and District priorities change.

Construction Projects

Planned Project Estimated Amount Amount Spent to Date

$52,031,731.13

$5,002,852.88

Amanecer Elementary (J) (East) $2,485,525.00 $0.00
Bonita Springs Elementary Renovation $15,687,505.51 $3,058,950.99
Cape Coral Technical College Expansion $5,490,435.97 $1,853,393.25
Franklin Park Rebuild $3,670,439.00 $0.00
Gateway High $12,037,738.00 $0.00
Lehigh Middle Addition-MM $942,880.00 $0.00
Lehigh Senior Addition $858,012.00 $0.00
Lemuel Teal Remodel (Old LAMS) $1,703,998.21 $25,635.24
Middle School MM $6,128,656.00 $0.00
Riverdale High Remodel $2,344,387.63 $28,305.00
Veterans Park Remodel $94,447.01 $2,000.00
Veterans Park/Lemuel Teal MS Black Box Theatre $587,706.80 $34,568.40

Maintenance Projects

Planned Project Estimated Amount Amount Spent to Date

$91,060,815.44

$2,064,164.18

Air Conditioning (HVAC) $25,665,262.24 $201,877.66
Auditorium Seating $0.00 $0.00
Building Improvements $12,953,177.07 $415,938.64
Electrical & Lighting Replacements/Upgrades $2,751,819.85 $286,791.44
Fire Alarm/Sprinkler System Improvements/Upgrades $3,073,989.07 $372,886.13
Floor Coverings $9,659,957.84 $690,305.48
PE & Playground Improvements $1,524,107.00 $0.00
Roof Replacements $20,754,996.65 $63,705.65
School Equipment $5,200,000.00 $0.00
Site Improvements (Drainage, Landscaping, etc.) $1,761,330.72 $32,659.18
Windows $7,716,175.00 $0.00

Safety Projects

Planned Project Estimated Amount Amount Spent to Date

$12,941,252.03

$738,884.58

Other Safety Improvements $161,667.24 $69,679.23
Safety Upgrades $11,037,084.79 $669,205.35
Single Point Entry (Physical & Technology) $1,742,500.00 $0.00

Technology Projects

Planned Project Estimated Amount Amount Spent to Date

$3,850,190.57

$3,563,468.08

Increased Elementary Computer Density $2,000,959.24 $1,867,353.33
Modernized Interactive A/V Systems (ATLAS) $1,849,231.33 $1,696,114.75

Charter Disbursements

Charter School Estimated Amount Amount Spent to Date

$20,265,226.00

$10,965,438.65

Charter Disbursements $20,265,226.00 $10,965,438.65