FY 25-26 (Year 8)

Sales Tax Revenue
JULY 2025 - JUNE 2025

Planned Projects

*Revenue estimates and projects are subject to modification as actual data and District priorities change.

Construction Projects

Planned Project Estimated Amount Amount Spent to Date

$114,398,880.11

$15,631,004.01

Amanecer Elementary (J) (East) $2,488,146.00 $0.00
Bonita Springs Elementary Renovation $36,276,671.58 $2,495,064.98
Cape Coral Technical College Expansion $22,282,890.96 $2,923,495.49
Franklin Park Rebuild $3,675,106.00 $0.00
Gateway High $12,045,307.00 $0.00
Lehigh Middle Addition-MM $938,055.00 $0.00
Lehigh Senior Addition $856,693.00 $0.00
Lemuel Teal Remodel (Old LAMS) $3,126,343.19 $1,235,438.86
Middle School MM $6,129,893.00 $0.00
Other Safety Improvements $2,107,375.41 $359,799.27
Riverdale High Remodel $21,576,646.35 $7,347,114.38
Veterans Park Remodel $2,372,828.99 $1,180,980.67
Veterans Park/Lemuel Teal MS Black Box Theatre $522,923.63 $89,110.36

Maintenance Projects

Planned Project Estimated Amount Amount Spent to Date

$23,700,206.72

$8,888,913.09

Air Conditioning (HVAC) $9,176,644.53 $4,038,031.36
Building Improvements $4,888,420.49 $1,414,011.79
Electrical & Lighting Replacements/Upgrades $1,855,432.07 $822,493.15
Fire Alarm/Sprinkler System Improvements/Upgrades $1,993,200.03 $187,358.41
Floor Coverings $3,608,272.50 $2,309,338.13
PE & Playground Improvements $25,225.75 $3,991.75
Roof Replacements $157,594.10 $1,131.25
School Equipment $96,032.25 $96,032.25
Site Improvements (Drainage, Landscaping, etc.) $1,832,000.00 $0.00
Windows $67,385.00 $16,525.00

Safety Projects

Planned Project Estimated Amount Amount Spent to Date

$14,273,613.06

$1,017,517.70

Safety Upgrades $11,773,613.06 $1,017,517.70
Single Point Entry (Physical & Technology) $2,500,000.00 $0.00

Technology Projects

Planned Project Estimated Amount Amount Spent to Date

$23,597,542.88

$679,527.71

Increased Elementary Computer Density $17,734,119.88 $22,649.21
Modernized Interactive A/V Systems (ATLAS) $5,863,423.00 $656,878.50